Travis Elementary School Renovation

Built in 1926, Travis Elementary underwent a major renovation project. All buildings were demolished with the exception of the old main building.

Mobile Enterprises, Inc. was contracted to remove all the old wood forms from original construction from the crawl space and repair CIP joists where exposed steel was corroding and weakening the structure.

Working in very difficult areas, Mobile crews repaired 900 Linear Feet of joists and cracks utilizing experienced foremen and technicians. Job was completed on time and within original budget.

Project: Travis Elementary Renovation

Owner: Houston ISD

System: Sika 123+ / Sika 52

Area: 900 Linear Feet

Completed: February 2006

Before

After