Four Leaf Towers Emaco

Before

A raging fire swept through portions of the fifth, sixth and seventh floor of the Four Leaf Towers Condominiums located in Houston’s exclusive Post Oak / Galleria area.

Mobile’s crews installed an engineered shoring system and removed all unsound concrete and repaired with Master Builder’s Emaco R 350 CI and injected over 400 linear feet of crack utilizing the “SCB Process”.

Work was completed on time and within budget.

Project: Four Leaf Towers Fire Renovation Phase II

Owner: Four Leaf Towers Counsel
Houston, Texas

System: Master Builder’s R 350 CI Master Builder’s Concresive 1380 Injection Resin

Area: 453 Linear Feet Crack 100 Cubic Feet R 350 CI

Completed: September 2002