HCSC Corp Data Center Cooling Tower Basin Liner

Before

Mobile Enterprises, Inc. was selected by Alpha Insulation & Waterproofing to sandblast and install CIM 2000 60-mil seamless membrane at the two (2) new concrete cooling tower basin structures.

After sandblasting, bugholes in the concrete had to be filled with an epoxy paste and all exposed concrete had to be primed with epoxy.

To avoid excessive pin-holing and surface bubbles, the CIM membrane had to be installed during falling temperatures and could not be installed in direct sunlight.

Mobile Enterprises worked diligently to adhere to these strict installation requirements in order to furnish a seamless liner membrane.

Project: HCSC Corp Data Center –
Concrete Cooling Tower Basin Liner

Owner: Holder Construction and Alpha Insulation & Waterproofing, Inc.

System: CIM 2000

Area: 19,310 SF

Completed: May 2009

After