Seawall Reconstruction Project

Due to references from engineers, Mobile Enterprises, Inc. was selected by Gunther Nash/CCC Group to be the specialty contractor to perform parts of the Seawall Reconstruction Project, Contract B-2, Phase 2.

During this project, Mobile crews did the following work:

3,596 LF Concrete Sawing 22” deep
258 CF Dow Froth Pak Foam
1,550 LF WillSeal 600 1.5” x 3”
1,550 LF PolySpecThiokol 2235 M
759 SF Spall Repairs
1,703 LF Epoxy Injection
3,125 LF Acrylic Ester Injection
20,353 LF Rout & Seal Cracks
48 EA 4” x 18” Cores
62 EA 2” x 2” Cores

All work was done under stringent specifications and engineering approval.

The General Contractor, Engineer and Owner were all very pleased with the quality of Mobile Enterprises personnel and performance.

Project: Seawall Reconstruction Project
Contract B-2, Phase 2

Owner: City of Corpus Christi, Texas

Systems: CTS Rapid Set Mortar
Concresive Liquid LPL
Greenstreak MultiGel 850
Euclid Eucolastic 1
ProPoxy 300 Fast & 50
Dow Froth Pak
WillSeal 600
PolySpecThiokol 2235 M

Area: See Below

Completed: Spring 2005